Dáil Éireann Debate, Wednesday - 6 November 2024

Wednesday, 6 November 2024

Ceisteanna (83)

Eoin Ó Broin

Ceist:

83. Deputy Eoin Ó Broin asked the Minister for Education for an update on the large-scale project for a school (details supplied) under the School Building Programme; when the project is expected to reach the next stage; and if she will make a statement on the matter. [45488/24]

Amharc ar fhreagra

Freagraí scríofa

The school building project for the school referred to by the Deputy is being delivered under my Department’s Design and Build Programme as a campus project and will deliver a new 1,000 pupil post-primary school and accommodation, including 4 classrooms, for children with special educational needs and a new 16 classroom primary school and accommodation, including 2 classrooms, for children with special educational needs on the ETB-owned site at Fortunestown Lane.  

A Letter of Acceptance (LOA) issued to the successful contractor on 28th of June 2024, which allowed the contractor to mobilise to site. The works on site are progressing and the project is being delivered on a phased basis.

Roinn