526. Deputy Eoin Ó Broin asked the Minister for Education further to Parliamentary Question No. 88 of 23 October 2024, to provide an update on the large-scale project for a school (details supplied) under the school building programme; if a letter of acceptance has been issued; if a commencement date is available given the considerable delays already experienced by the school; and if she will make a statement on the matter. [3609/25]

Amharc ar fhreagra

Freagraí scríofa

The large scale capital project at the school referred to by the deputy is at an advanced stage of Architectural Planning Stage 3 - Tender Action and Award.

The second Tender Report for Reserved Specialists was reviewed by my Department and comments issued to the Design Team and DDLETB for action. When a satisfactory reply is received in relation to the queries raised, we will provide an update to the school authority.

This project remains a priority for delivery.