My Department provides funding directly to DCC for their programme of urban renewal. It also supports projects brought forward by the LDA which complements the regeneration programme.
The Montpelier project is currently on-site and will reach substantial completion in 2027 delivering 1,044 new homes including 280 social homes, 233 affordable purchase homes and 264 cost rental homes.
The Emmet Road Development will deliver 578 new homes comprising 137 social and 441 cost rental homes. Stage 3 approved in January 2025 and the project will reach substantial completion in 2028.
The LDA-led Donore Project will deliver 543 new homes, including 154 social homes alongside 389 LDA cost rental homes. Stage 3 approved in December 2024 and will reach substantial completion in 2028.
The LDA-led Bluebell Waterways Project will deliver 381 new homes including 148 social homes alongside 233 LDA cost rental homes. Stage 2 approved in December 2024 and will reach substantial completion in 2030.
The Dorset St Project will provide 163 social homes in 2026. This project received initial Capital Appraisal approval in March 2020 and is currently on-site
The Constitution Hill Project will provide 124 social homes across two phases in 2027. This project received initial Capital Appraisal approval in June 2020 and has received Stage 2 approval to proceed to planning for phase 1 (46 units) and Stage 3 Pre-tender approval for phase 2 (78 units).
The Cromcastle Court Project will provide 152 social homes in 2029. This project received initial Capital Appraisal approval in March 2021 and has received Stage 2 approval to proceed to planning.
The Dolphin House regeneration Project anticipates providing in excess of 798 mixed tenure homes. DCC are working on the stage 1 and an associated Strategic Assessment Report, which will finalise plans. They are also actively progressing the preparation of a planning application for an initial early phase of development at phase 1b.