The table below provides details of the project payments up to the end of May 2025:
|
Supplier Name
|
Pre-2021
€’000
|
2021
€’000
|
2022
€’000
|
2023
€’000
|
2024
€’000
|
2025
€’000
|
Total
€’000
|
Purpose / Desired Outcome
|
|
Accenture Consulting
|
22,710
|
5,915
|
2,102
|
0
|
263
|
101
|
31,091
|
System Integrator – Wave 1; Initial hardware and software purchases
|
|
EY
|
3,725
|
6,463
|
2,392
|
1,621
|
3,287
|
977
|
18,465
|
Client Service Partner and Advisory Services
|
|
Staff Costs
|
10,518
|
2,068
|
902
|
670
|
1,560
|
725
|
16,443
|
NSSO staff involved in project work such as business readiness, migration, functional design, testing, training etc
|
|
Deloitte
|
6,204
|
0
|
0
|
0
|
0
|
0
|
6,204
|
Advisory services
|
|
IBM
|
0
|
0
|
0
|
0
|
492
|
246
|
738
|
System Integrator
|
|
OPW
|
1,673
|
1
|
0
|
0
|
0
|
0
|
1,674
|
Building fit-out
|
|
Evros
|
1,485
|
1
|
15
|
0
|
0
|
0
|
1,501
|
Technical support
|
|
Oracle
|
935
|
322
|
3
|
1,680
|
481
|
0
|
3,421
|
Hardware upgrade and software maintenance
|
|
CPL Solutions Ltd
|
388
|
227
|
99
|
83
|
267
|
86
|
1,150
|
Technical support
|
|
Next Generation Ltd
|
644
|
0
|
0
|
0
|
0
|
0
|
644
|
Technical support
|
|
Others
|
4,102
|
176
|
163
|
206
|
28
|
1
|
4,676
|
Various project costs and overheads
|
|
Gross Expenditure
|
52,384
|
15,173
|
5,676
|
4,260
|
6,378
|
2,136
|
86,007
|
|
|
Receipts
|
-53
|
-143
|
0
|
0
|
-8
|
-1
|
-205
|
EU Funding for eInvoicing and various staff-related receipts
|
|
Net Expenditure
|
52,331
|
15,030
|
5,676
|
4,260
|
6,370
|
2,135
|
85,802
|
|
The desired outputs from the project will be:
• the standardisation of accounting processes across central government;
• the modernisation of finance in government with end to end integrated financial controls;
• compliance with existing and emerging international reporting and transparency requirements and agility in responding to further changing international reporting requirements;
• a platform for compliance with EU directives in eProcurement;
• support for the professionalisation of finance teams across government; and
• enhanced and enriched financial data to enable data analytics.