290. Deputy Michael Murphy asked the Minister for Justice, Home Affairs and Migration further to Parliamentary Question No. 415 of 12 June 2025, if he will provide a detailed summary of costs solely associated with the delivery of the modular units in Clonmel. [35244/25]

Amharc ar fhreagra

Freagraí scríofa

Works are now nearing completion at the final site of the Rapid Build programme, in Haywood, Clonmel. This will bring the final output of the programme to 654 homes, with the capacity to accommodate 2,640 people fleeing the war in Ukraine.

I am advised that a detailed summary of costs specific to the units in Clonmel as sought by the Deputy is not yet available as the full programme has not reached completion.