Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Electricity Generation

Dáil Éireann Debate, Thursday - 18 September 2025

Thursday, 18 September 2025

Ceisteanna (146)

Louis O'Hara

Ceist:

146. Deputy Louis O'Hara asked the Minister for Climate, Energy and the Environment the progress made in the development of flexible electricity generation capacity; and if he will make a statement on the matter. [49078/25]

Amharc ar fhreagra

Freagraí scríofa

The Government has set a target of having at least 2GW of new, flexible, gas-fired generation capacity by 2030 in our Climate Action Plans to ensure secure generation of electricity at time of low renewable output and/or high demand. This allows for the integration of a large volume of wind and solar electricity projects that displace the need to run fossil fuel plants for baseload, without compromising security of supply. In addition, increasing amounts of batteries, long duration storage, interconnector capacity and demand side response have also been procured in recent capacity market auctions which will lessen Ireland's dependence on fossil fuel imports in the coming years.

Dispatchable generation capacity is procured through the Capacity Remuneration Mechanism (CRM) under the overall regulatory supervision of the Single Electricity Market Committee (SEMC). The dispatchable generation capacity sought via the CRM auctions are delivered by developers in the open market to be enduring capacity that will support an up to 80% renewable powered electricity system into the 2030s. The successful and expeditious delivery of all capacity market projects is a critical component in ensuring enduring security of supply.

Question No. 147 answered with Question No. 132.
Roinn