Dáil Éireann Debate, Wednesday - 8 October 2025

Wednesday, 8 October 2025

Ceisteanna (118)

Matt Carthy

Ceist:

118. Deputy Matt Carthy asked the Minister for Housing, Local Government and Heritage the current status of Phase 3 of the Ulster Canal; when works on this phase are expected to commence; and the estimated date of completion. [53807/25]

Amharc ar fhreagra

Freagraí scríofa

The restoration of the Ulster Canal is a major cross-border project principally funded by the Shared Island Fund and my Department. The project is being delivered by Waterways Ireland, in three phases:

• Phase 1 from Upper Lough Erne to Castle Saunderson (completed in 2019)

• Phase 2 from Clones to Clonfad (completed June 2024), and

• Phase 3 Castle Saunderson to Clonfad (underway).

Phase 3 is the longest stretch at 10km and includes 10km of new and refurbished navigable canal and towpath, bridges, locks, marina and service blocks. Phase 3 has four sub-phases of which three (sub-phases 3.1, 3.2 and 3.4) will be progressed first:

• Sub-phase 3.1 from Castlesaunderson to Gortnacarrow

• Sub-phase 3.2 from Gortnacarrow to Clonoony

• Sub-phase 3.3 Clonoony to Derrynure

• Sub-phase 3.4 Derrynure to Clonfad

Substantial preliminary work is underway on Phase 3. Waterways Ireland has appointed a dedicated project lead for this phase and detailed design tenders for sub-phases 3.1 and 3.2 issued in April this year.

Waterways Ireland continues to liaise with relevant stakeholders including affected landowners in relation to the project. Waterways Ireland has corresponded with all affected landowners, providing a project update, and more detailed engagement has commenced recently with land owners in sub phases 3.1 and 3.2.

Estimated completion of all elements (subject to land acquisition and the necessary planning consent for sub-phase 3.3) is 2029.