324. Deputy Barry Heneghan asked the Minister for Housing, Local Government and Heritage the number of new social and affordable homes delivered in Dublin bay north in 2024 and to date in 2025; and if he will make a statement on the matter. [62561/25]

Amharc ar fhreagra

Freagraí scríofa

Delivery data is not available on a constituency basis, however my Department publishes comprehensive programme-level statistics on a quarterly basis on social and affordable housing delivery activity by local authorities and Approved Housing Bodies (AHBs) in each local authority. This data is available to the end of Q2 2025 and is published on the statistics page of my Department’s website at the following link: www.gov.ie/en/collection/6060e-overall-social-housing-provision/.

My Department also publishes the Social Housing Construction Status Report (CSR), which provides details of social housing developments and their location that have been completed, are under construction or are progressing through the various stages of the design and tender processes. The most recent publication was for Quarter 2 2025. All CSRs are available at the following link: www.gov.ie/en/collection/cb885-social-housing-construction-projects-status-reports/.

A version of the CSR file can also be downloaded for analysis by local authority, location etc. at this link: http://opendata.housing.gov.ie/dataset/social-housing-construction-status-report-q2-2025.