412. Deputy John Paul O'Shea asked the Minister for Education and Youth the status of a capital project for a school (details supplied); the details of the works involved; the timeline for completion of the project; and if she will make a statement on the matter. [71099/25]

Amharc ar fhreagra

Freagraí scríofa

The school referred to was approved funding under the Department’s Additional School Accommodation Scheme or conversion of existing space to provide a Principal’s Office, Secretary's Office, and Entrance Lobby.

In December 2024, the Department authorised the project to proceed to construction, and the school has since confirmed that works have been completed.