St Thomas JNS & Scoil Áine SNS
The joint school building project will deliver two new 24 classroom primary schools with accommodation for children with special educational needs, at the current site in Lucan.
The project is currently at an early stage of Architectural Planning Stage 1 – Initial Sketch Scheme. A preferred design option has been agreed by all Stakeholders and my Department have requested the Design Team to further assess the proposed construction programme and methodology.
The stage 1 report was received by my Department in May 2025 and is currently under review. Upon completion of the review, my Department will advise both schools and their design team regarding project progression.
Devine Mercy JNS & SNS
This joint school building project will deliver a new extension and refurbishment of some existing accommodation to provide a 24 classroom primary school with classrooms for children with special educational needs, at both schools.
The schedule of accommodation was recently increased to include SEN accommodation and the design options submitted by the Design Team are being evaluated by my Department.
A meeting of all stakeholders is anticipated to be held in the near future, to discuss and agree a preferred option which can be further developed and prepared to be submitted for planning permission.
Lucan Community College
The major building project for the school referred to by the Deputy is a large scale capital project for the construction of a new extension and the refurbishment of existing facilities to accommodate 1,000 pupils, including provision for Special Educational Needs (SEN) classrooms.
More than four years has elapsed since the publication of the contract notice and more than two years since the tender submission deadline. Given the passage of time since tenders were returned and the unacceptably high risk that the contract may not successfully be delivered within budget, the ETB were instructed to collapse the tender procedure in July 2025.
My Department officials have engaged with the ETB and School Principal and have proposed to progress a phase 1 of this project through my Department’s timber modular framework which offers an extremely high quality finish and fast delivery.
The proposal relates to Phase 1 of the school extension, covering a gross internal floor area of 1,500 m² includes the superstructure and internal finishes containing additional accommodation for 204 pupils and 4 additional classrooms for pupils with Special Educational Needs with sufficient flexibility to cater for subsequent phases on the site.
St Kevin's Community College
In respect of the schools existing accommodation, an Emergency Works Scheme (EWS) application was submitted by the school for works associated with universal accessibility. A tender report was recently received from the school and the EWS area is engaging with the school regarding some additional information on this report. The EWS area is aware of the urgent nature of the works required and will continue to support the school in this regard.
In July the Government announced a capital allocation of €7.55 billion for the Department of Education and Youth for the period 2026-2030 under the National Development Plan. As part of this NDP allocation my department will place a strong emphasis on provision for children with special educational needs, with a particular focus on meeting annual school place needs. In relation to project rollout for Large-Scale projects and Additional School Accommodation scheme projects, the approach will be to continue to maximise the capacity of the existing school estate as much as possible in the first instance and provide necessary additional capacity through targeted and prioritised project rollout over the course of 2026 to 2030 period to meet the most urgent and prioritised needs.
Government departments are currently in the process of publishing their sectoral NDP Implementation Plans. The sectoral plan for the Education and Youth sector will be published next week and the first tranche of projects to progress to construction will be published in January. This NDP Implementation Plan will optimise outputs from the NDP allocations, with a strong focus on maximising existing school capacity, progressing priority projects where local capacity across schools in the area is insufficient, and ensuring delivery that is affordable, offers value for money, and meets functional needs.