As the Deputy knows, imperfections and dispatch down are a major challenge facing the electricity system. Obviously, dispatch down is brought about by constraints on the grid and the challenges of getting the electricity from the point of generation to where there is a demand and a need. If the grid is not capable of carrying the electricity at a particular time, energy generators are required to effectively stop generating so that there is not more complexity on the grid. This complex issue can only be addressed by taking a systematic and multifaceted approach, requiring investment in grid, storage and demand flexibility. We are already taking steps to invest in this critical energy infrastructure and, for example, PR6 will enable the delivery of over 500 capital network projects supporting the integration of increasing volumes of renewable energy and helping to reduce the amount of wasted energy in the first instance.
In July the Government committed to investing €3.5 billion of national development plan, NDP, funding in EirGrid and ESB Networks in order to ensure that the PR6 infrastructure programme can be delivered. That level of investment by the State in ESB Networks and EirGrid provides those companies with capacity to leverage against significant further borrowing that will ensure we will see a very significant upgrade of our networks. Legislation providing the legal mechanism necessary for the investment of €1.5 billion of this funding into ESB Networks has now passed all Stages and was signed into law by the President last month. Further legislation in relation to the investment in EirGrid will be progressed next year.
Last year the Department published the electricity storage policy framework for Ireland which supported the procurement of 500 MW of demand flexibility products by ESB Networks and 500 MW of long-duration electricity storage by EirGrid to meet specific network needs. Work is already under way to ensure the timely delivery of those projects.