Rail Network

Dáil Éireann Debate, Tuesday - 27 January 2026

Tuesday, 27 January 2026

Ceisteanna (317)

Barry Heneghan

Ceist:

317. Deputy Barry Heneghan asked the Minister for Transport the details of all works completed since 2020 and all works planned for the period 2026 to 2030 at DART stations and platforms on the northside of Dublin (details supplied); the type of works carried out or proposed in each station; the year of completion or planned delivery; the current status and the funding source of each, in tabular form; and if he will make a statement on the matter. [5850/26]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy may be aware, the National Transport Authority (NTA) has responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area (GDA) including, in consultation with Iarnród Éireann, the DART+ programme.

The DART+ programme which comprises five different projects in and around the GDA will triple the length of the electrified rail network from circa 50km to 150km and double city centre capacity from 26,000 passengers per hour per direction to 52,000 during peak hours. This will significantly enhance access to high capacity public transport across the GDA.

As part of the DART+ programme, DART+ Coastal North will provide an extension of DART services from Malahide to Drogheda.

The Railway Order for DART+ Coastal North was approved by An Coimisiún Pleanála in August 2025.

The DART+ fleet project provides a ten-year procurement framework for electric and battery-electric train fleet. Three fleet orders have been placed comprising 285 battery-electric and electric carriages. The first order for the purchase of 95 additional DART carriages, which compromise of 65 battery-electric carriages and 30 electric carriages, have started arriving in Ireland and are currently undergoing certification and safety testing. It is intended that the new battery-electric sets will be initially deployed on the Northern Commuter Line serving Dublin to/from Drogheda from 2027, which will provide additional capacity on the line.

The NDP Sectoral Investment Plan published by my Department in November 2025 notes that there is also potential to commence works on elements of DART+ Coastal North, including supporting infrastructure such as track passing loops and a new platform at Drogheda station, prior to 2030, in advance of works on Overhead Line Equipment (OHLE).

Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a more detailed reply. Please contact my private office if you do not receive a reply within 10 days.

A referred reply was forwarded to the Deputy under Standing Orders.