As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has the statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area (GDA), which includes MetroLink.
The Railway Order for MetroLink was published by An Coimisiún Pleanála on October 2, 2025, representing a major milestone for the programme.
In November 2025, Government approved a policy proposal to establish a dedicated MetroLink delivery body and the preparation of legislation to give effect to this proposal.
As stated in the National Development Plan Review 2025, the Government will support MetroLink’s construction through €2 billion funding from the Infrastructure, Climate and Nature Fund.
A Detailed Project Brief and Procurement Strategy will be prepared for consideration at Approval Gate 2, in line with the Infrastructure Guidelines.
Construction of MetroLink is earmarked to commence over the coming years with a view to operation in the 2030s.
Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a detailed reply. Please contact my private office if you do not receive a reply within 10 days.