In order to plan for school provision and analyse the relevant demographic data, my department divides the country into 314 school planning areas and uses a geographical information system, using data from a range of sources, including CSO census data, child benefit and school enrolment data, to identify where the pressure for school places across the country will arise and where additional school accommodation is needed at primary and post-primary level.
Since 2020, my department has invested over €105 million in school infrastructure across Co. Offaly. The department is continually planning for and investing in existing and new schools to ensure that every child in the State has access to a school place.
If additional accommodation is required, the aim is to try and facilitate this, as much as possible, by way of expansion of existing schools rather than establishing new schools. The expansion of existing schools is consistent with wider Government objectives under Project Ireland 2040 for an increased emphasis on compact growth.
My department’s NDP Sectoral Investment Plan 2026-2030 involves a very strong emphasis on maximising existing capacity and prioritisation of school building projects to meet the most urgent needs. Of the total €7.55 billion investment it is envisaged that circa. €5 billion will be used for project rollout to support the delivery and modernisation of school buildings across the Large Scale, Additional Accommodation, Modular, and Annual September Accommodation Needs programmes. Over the course of 2026 and 2027 there will be construction work at circa. 10% of the school estate. These projects will, when completed, provide circa 57,000 additional and modernised school places with a strong SEN focus in all projects.
The first tranche of 105 projects covers the initial two-year period of NDP rollout. The next tranche of projects will be finalised and published afterwards (post 2027) following a stakeholder engagement process to identify the next most urgent priorities. This stakeholder engagement will be undertaken in 2026 and 2027 and will include an assessment of how well existing capacity is maximised and enrolment policies and processes are prioritising local special education provision and mainstream requirements. The Department-led Energy and Condition Survey of the school estate, which will be finalised later in 2026, will provide an additional evidence base for assessing priorities.
The criteria for identifying the first tranche of 105 prioritised projects to go to construction / tender in 2026 and 2027 included the condition of the school, projects in areas with capacity pressures, growing demographics and projects in the pipeline for a long time. The 105 prioritised projects consist of 80 large-scale and ASA (additional school accommodation) projects along with 25 projects to be delivered under the Modular Accommodation Programme.
My Department will continue to liaise with Offaly County Council in respect of their county development plan and any associated local area plans with a view to identifying potential evolving long-term school accommodation requirements across school planning areas.