School Facilities

Dáil Éireann Debate, Thursday - 12 February 2026

Thursday, 12 February 2026

Ceisteanna (178)

Mark Ward

Ceist:

178. Deputy Mark Ward asked the Minister for Education and Youth for an update on the schools that were awarded funding through the 2026 summer works programme in Dublin mid-west; and if she will make a statement on the matter. [11051/26]

Amharc ar fhreagra

Freagraí scríofa

The purpose of the Climate Action Summer Works Scheme (CASWS) is to enable individual school authorities to undertake small-scale building works on a devolved basis that, ideally, can be carried out during the summer months or at other times that avoid disrupting the operation of the school. The CASWS operates on a multi-annual basis across a number of categories of works.

It is envisaged that approvals in any given year will involve a spread of categories rather than the traditional single category at a time. This is aimed at managing market capacity and maximising value for money opportunities for school authorities.

In November 2025, my colleague the former Minister of Education and Youth, Helen McEntee TD, announced the first tranche of approvals under the new Climate Action Summer Works Scheme. 297 projects were approved to proceed and involve primary, post primary and special schools, along with projects in all counties and across all categories of works.

All schools approved in November 2025 have been notified of their approval and advised as to the next steps in order to progress their CASWS projects. As the CASWS is a devolved scheme it is now with the schools to progress their project to the next stage.

Full details of the of the announcement and the list of schools approved in the first tranche, the Circular (0029/2025) for the scheme and guidance documents for schools can be found at the below link;

gov.ie Summer Works Scheme.