School Facilities

Dáil Éireann Debate, Thursday - 12 February 2026

Thursday, 12 February 2026

Ceisteanna (352)

Emer Currie

Ceist:

352. Deputy Emer Currie asked the Minister for Education and Youth for an update regarding an additional accommodation project under the School Capital Programme (details supplied); and if she will make a statement on the matter. [11292/26]

Amharc ar fhreagra

Freagraí scríofa

The school referred to by the Deputy has been approved to enter my department’s pipeline for school building projects, to provide four mainstream classrooms and two science labs under my department’s SEN Repurposing and Modular Accommodation programme as Phase 1 of this school permanent extension. As part of this project, ongoing repurposing works within the school are also being carried out to create two special educational needs classrooms.

Phase 2 of the development has been approved under the Additional School Accommodation Scheme. The approved works includes the provision of seven mainstream classrooms, one music room, one design and computer graphics room, one home economics room, one graphics room, two engineering, construction studies and technology rooms with preparation areas, two special educational needs classrooms, two special education tuition rooms, one office, one staff room, and ancillary accommodation. The project was devolved to Dublin and Dún Laoghaire Education and Training Board (DDLETB) for delivery.

My department is still awaiting receipt of the Stage 1 (Preliminary Design) report from the appointed design team, and we have not yet been advised of the expected delivery date. It is now within the remit of DDLETB to progress this project accordingly

As the Deputy will be aware, I have recently published the €7.55 billion NDP Sectoral Investment Plan for the Education and Youth Sectors for the period 2026 to 2030. This NDP Sectoral Plan involves a very strong emphasis on maximising existing capacity and prioritisation of school building projects to meet the most urgent needs. In this regard there will be a strong special education dimension to project rollout.

Of the total €7.55 billion investment it is envisaged that circa. €5 billion will be used for project rollout to support the delivery and modernisation of school buildings across the Large Scale, Additional Accommodation, Modular, and Annual September Accommodation Needs programmes. Over the course of 2026 and 2027 there will be construction work at circa. 10% of the school estate. These projects will, when completed, provide circa 57,000 additional and modernised school places with a strong SEN focus in all projects.

My department will continue to build on the progress made over recent years with the continued rollout of projects on a prioritised basis to meet the most urgent needs in terms of provision of additional capacity and modernisation of existing facilities. In this regard, I have also published a list of the 105 school building projects in the first tranche to proceed to construction or tender over 2026 and 2027.

The first tranche of 105 school building projects includes 80 large scale and Additional School Accommodation scheme projects. These projects were prioritised with a strong focus on maximising existing capacity and prioritising project rollout to meet the most urgent needs particularly to support special education needs provision.

Firstly, to facilitate the 45 projects that are currently already at tender stage (Stage 3) so that they can progress to construction as smoothly as possible over the course of 2026 and 2027. Secondly, to facilitate 35 projects that currently have planning permission and are at pre-tender stage (Stage 2b) and have been prioritised to meet urgent requirements from a special needs perspective or to provide additional capacity to cater for demographics or to address very significant condition issues at the schools.

I recognise that there are schools with important building projects that are not included in the first tranche of prioritised projects.

As part of planning ahead for the next tranche of projects to progress to tender, the department-led prioritisation process will continue over the course of 2026 and 2027 to assess and evaluate the progression of individual projects through the design pipeline having regard to the continual need to maximise existing capacity and determine the prioritised needs going forward. This process will involve engagement with key stakeholders and individual schools and will ultimately inform the next tranches of programme rollout to tender. The department-led Energy and Condition Survey of the school estate, which will be finalised later in 2026, will provide an additional evidence base for assessing priorities.

Based on this ongoing prioritisation process some projects may be added to the list over the course of 2026 and 2027 having regard to their prioritisation and urgency of need and taking account also of the ongoing ability to progress them to tender and construction within the parameters of overall funding. Where appropriate, the department will also assess opportunities to undertake advance enabling works for the most urgent and complex projects to facilitate a smooth progression to construction in 2028 and beyond.

Any interim accommodation requirements will continue to be assessed and considered by the department on a case-by-case basis to determine the prioritised needs and approach for addressing same.

The accommodation needs at this school will be considered as part of the ongoing overall department-led prioritisation process, in consultation with the school’s patron and school authorities.