Schools Building Projects

Dáil Éireann Debate, Thursday - 26 March 2026

Thursday, 26 March 2026

Ceisteanna (287)

Brendan Smith

Ceist:

287. Deputy Brendan Smith asked the Minister for Education and Youth the progress to date in advancing a project (details supplied); when this proposal will advance to the next stage; and if she will make a statement on the matter. [23463/26]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy is aware the school was approved under the Additional Accommodation Scheme to provide eight general classrooms, four special education tuition rooms, one music room, one textiles room, one art room, one multimedia room, two science laboratories and preparation area, one library and a general purpose/dining hall.

The Stage 2b report submitted in October 2025 remains under review. Given the scale and complexity of this project the Stage 2b report will require a thorough and intensive review from both a technical and cost perspective. All projects, including this one, will undergo the necessary due diligence as outlined in the Infrastructure Guidelines. Managing timing, scope, and cost is crucial to staying within budgetary limits for the overall program.

Although this project is not within the first tranche of school building projects recently published in the NDP Sectoral Investment Plan, it remains part of the Department’s overall pipeline of school building projects. The NDP Sectoral Plan involves a very strong emphasis on maximising existing capacity and prioritisation of school building projects to meet the most urgent needs. In this regard there will be a strong special education dimension to project rollout.

As part of planning ahead for the next tranche of projects to progress to tender, the department led prioritisation process will continue over the course of 2026 and 2027 to assess and evaluate the progression of individual projects through the design pipeline having regard to the continual need to maximise existing capacity and determine the prioritised needs going forward. This process will involve engagement with key stakeholders and individual schools and will ultimately inform the next tranches of programme rollout to tender. The department-led Energy and Condition Survey of the school estate, which will be finalised later in 2026, will provide an additional evidence base for assessing priorities.

Based on this ongoing prioritisation process some projects may be added to the list over the course of 2026 and 2027 having regard to their prioritisation and urgency of need and taking account also of the ongoing ability to progress them to tender and construction within the parameters of overall funding. Where appropriate, the Department will also assess opportunities to undertake advance enabling works for the most urgent and complex projects to facilitate a smooth progression to construction in 2028 and beyond.

Any interim accommodation requirements will continue to be assessed and considered by the department on a case-by-case basis to determine the prioritised needs and approach for addressing same.

The accommodation needs at this school will be considered as part of the ongoing overall department led prioritisation process, in consultation with the school’s patron and school authorities.