Renewable Energy Generation

Dáil Éireann Debate, Thursday - 16 April 2026

Thursday, 16 April 2026

Ceisteanna (140)

Louis O'Hara

Ceist:

140. Deputy Louis O'Hara asked the Minister for Climate, Energy and the Environment his plans to reduce waiting times for the solar PV scheme for medically vulnerable customers; and if he will make a statement on the matter. [27081/26]

Amharc ar fhreagra

Freagraí scríofa

The Solar PV for the Medically Vulnerable Scheme is a targeted scheme for the installation of solar photovoltaic (PV) panels for customers/households who are registered on the life support category of the Priority Services Register. These homes have a dependence on electrically powered equipment, including medical equipment, life protecting devices and assistive technologies such as dialysis machines and respirators. As such, these households may have a higher energy demand than the average user and this scheme is designed to go some way towards helping to reduce those energy costs.

The scheme is operated by the Sustainable Energy Authority of Ireland (SEAI) in conjunction with energy suppliers, with each energy supplier contacting their own eligible customers directly, in line with the work plans for their solar PV installers. Eligible households can avail of a fully funded 2kWp solar PV system, including survey/design, supply, installation, and the post works BER.

It is important to note that suppliers, who manage the administrative aspects of the scheme under the SEAI, issue offers to eligible homeowners. Each participating supplier received an allocated amount of funding under their Memorandum of Understanding with the SEAI and contacts eligible households in batches, based on operational capacity.

Due to the strong uptake, eligibility for the scheme was extended in November 2025 to include all homeowners who are registered under the life support category of the Priority Services Register with their energy supplier, regardless of when they were registered, as long the house is built and occupied on or before 31 December 2020.

Over 470 systems were installed last year with expenditure of €2.4 million. This year will see a major expansion of delivery with an allocation of €11.7 million to support over 1,900 homes.