71. Deputy John Clendennen asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation if he will provide an update on plans for upgrade or refurbishment works at Kilcormac Garda Station, County Offaly in 2026; the scope of any such works; the budget allocated; the current stage of the project; and the expected timeline for commencement and completion; and if he will make a statement on the matter. [29132/26]

Amharc ar fhreagra

Freagraí scríofa

The Office of Public Works (OPW) can confirm that works to upgrade the day room toilets are underway at Kilcormac Garda Station, County Offaly.  These works commenced in Q4, 2025, and are due to be completed in Q2, 2026. 

The project budget will be available following the completion of the works.