Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Healthcare Infrastructure Provision

Dáil Éireann Debate, Wednesday - 6 May 2026

Wednesday, 6 May 2026

Ceisteanna (1070, 1071, 1073, 1093, 1095, 1096, 1097, 1108)

Ken O'Flynn

Ceist:

1070. Deputy Ken O'Flynn asked the Minister for Health to outline the approval process for the capital funding allocated to the Heather House Community Nursing Unit project, including the stages of approval, the approving authority at each stage, and whether any revised cost approvals have been required since project commencement. [32662/26]

Amharc ar fhreagra

Ken O'Flynn

Ceist:

1071. Deputy Ken O'Flynn asked the Minister for Health whether the projected total cost of €10.69 million for the Heather House Community Nursing Unit project is fixed or subject to revision; and whether any cost overruns or revised projections have been identified to date. [32663/26]

Amharc ar fhreagra

Ken O'Flynn

Ceist:

1073. Deputy Ken O'Flynn asked the Minister for Health the original planned commencement and completion dates for the Heather House Community Nursing Unit refurbishment project; the current projected completion date; and the reasons for any delays arising. [32665/26]

Amharc ar fhreagra

Ken O'Flynn

Ceist:

1093. Deputy Ken O'Flynn asked the Minister for Health to provide a detailed breakdown of the €10.69 million projected cost of the fire safety and refurbishment works at Heather House Community Nursing Unit, including the original approved budget, the current projected outturn cost, the value of all additional works identified during construction, and the total cost variance arising to date. [32705/26]

Amharc ar fhreagra

Ken O'Flynn

Ceist:

1095. Deputy Ken O'Flynn asked the Minister for Health to provide details of the procurement process for the works at Heather House Community Nursing Unit, including the number of tenderers, the contract award value, the successful contractor, and whether any post-award variations have altered the contract value. [32707/26]

Amharc ar fhreagra

Ken O'Flynn

Ceist:

1096. Deputy Ken O'Flynn asked the Minister for Health to outline the governance and oversight arrangements in place for the capital works at Heather House Community Nursing Unit, including reporting structures, risk management processes, and whether any issues identified during construction were escalated to the Department. [32708/26]

Amharc ar fhreagra

Ken O'Flynn

Ceist:

1097. Deputy Ken O'Flynn asked the Minister for Health to specify the exact nature of the issues identified during the refurbishment works at Daisy Unit, Heather House Community Nursing Unit which led to the extension of the project timeline; whether these issues relate to structural defects, fire compliance, asbestos, design deficiencies, or contractor performance; and if she will provide a detailed breakdown of each issue identified. [32709/26]

Amharc ar fhreagra

Ken O'Flynn

Ceist:

1108. Deputy Ken O'Flynn asked the Minister for Health what capital funding, if any, was allocated or approved to address the infrastructural fire safety risks identified in the October 2024 assessment of the Daisy Unit, Heather House Community Nursing Unit; the estimated cost of required remediation works; and whether such works were progressed prior to the decision to close the unit. [32732/26]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 1070, 1071, 1073, 1093, 1095, 1096, 1097 and 1108 together.

As the Health Service Executive is responsible for the delivery of public healthcare infrastructure projects, I have asked the HSE to respond to you directly in relation to this matter.

Question No. 1071 answered with Question No. 1070.
Question No. 1072 answered with Question No. 1069.
Question No. 1073 answered with Question No. 1070.
Question No. 1074 answered with Question No. 1068.
Question No. 1075 answered with Question No. 1068.
Question No. 1076 answered with Question No. 1068.
Roinn