National Development Plan

Dáil Éireann Debate, Thursday - 7 May 2026

Thursday, 7 May 2026

Ceisteanna (272)

Brian Brennan

Ceist:

272. Deputy Brian Brennan asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation if he will provide a list of all capital projects delivered under the National Development Plan and otherwise within the remit of his Department, including the Office of Public Works, which have been completed on time and within budget in the Wicklow Wexford Constituency in each of the past five years, in tabular form; and if he will make a statement on the matter. [33929/26]

Amharc ar fhreagra

Freagraí scríofa

The Office of Public Works is a key service provider to Government, managing the State's estate portfolio, maintaining and presenting Ireland's built heritage, and leading the State's flood risk management function. Under the current National Development Plan, the OPW has secured a record allocation of €1.845 billion, encompassing flood risk management, State property management, and the conservation of heritage assets in support of regional tourism. The OPW's capital programme is therefore one of the most geographically distributed and functionally diverse in the public service, with works delivered in every county.

Under Estate Management, the OPW is responsible for the maintenance, refurbishment, and development of government properties, including offices, Garda stations, and other public service buildings. This includes energy efficiency upgrades and compliance with health and safety and climate obligations. New construction and fit-outs are also undertaken to meet evolving service needs, alongside property acquisitions and disposals as required.

Across the OPW estate ongoing maintenance is essential to ensure that public assets remain safe, functional, and efficient. Regular maintenance activities often identify areas where more substantial interventions are needed, leading to planned preventative capital works. These projects are designed to proactively address emerging issues, extend the lifespan of assets, and optimise their performance. By integrating insights from ongoing maintenance into capital planning, the OPW ensures that resources are used effectively and future risks are minimised.

With regard to capital projects completed by Estate Management in the last five years in Wicklow/Wexford area, some examples are, Wicklow Garda Station Kitchen and Facility upgrade, Tinahely Garda Station Universal Access plus a number of upgrade projects at Enniscorthy Garda Station. Please find list attached in tabular form as requested.

Heritage Services projects focus on the conservation, restoration, and presentation of nationally significant sites such as Glendalough. These works include structural repairs, preservation of architectural features, and enhancement of visitor facilities. The OPW’s efforts ensure that heritage assets are protected and accessible, supporting both cultural preservation and regional tourism.

Flood Risk Management is another core pillar, with the OPW leading the planning and delivery of flood relief schemes in conjunction with the local authorities. The OPW is working in partnership with both Wicklow County Council and Wexford County Council to advance major flood relief schemes and related works. Notable efforts include the very large schemes progressing for Arklow and Enniscorthy. These initiatives are supported by substantial Government investment, as reflected in the €6.6 million OPW funding announced last week for local authorities to deliver interim flood measures. The Flood Risk Management County Summary provides updates and can be viewed at the following link by selecting Wicklow & Wexford: www.floodinfo.ie/county-summary/.

Should you, Deputy, have a particular capital project in mind or wish to discuss any aspect of our planned preventative works in greater detail, I would welcome the opportunity to engage directly. Please feel free to contact me so we can address your specific interests and ensure your concerns are fully considered.

Year

Project Name ( Capital works over €0.2m)

Status

Delivered in line with Budget and timeline

2023

Wicklow GS - Kitchen and Facility upgrade

Complete

Yes

2024

Tinahely GS - Universal access works

Complete

Yes

2023

Enniscorthy GS - Cell and PPU upgrade

Complete

Yes

2024

Enniscorthy GS - ASU fit-out

Complete

Yes

2025

Enniscorthy GS - Boiler upgrade

Complete

Yes