Ongoing investment in and delivery of the Defence Forces Infrastructural programme enhances capability, personnel and organisational outcomes and has delivered positive benefits to military installations throughout the country. A number of important ongoing infrastructural projects set to progress significantly in the coming years.
The capital expenditure for building works in military installations and barracks across the country for the last five years was some €170 million.
This year the capital allocation stands at €69.5 million for capital investment. The information sought by the Deputy is as follows:
|
Year
|
Project Name
|
Cost incl. VAT
|
|
2025
|
DFTC, Transport Body Workshop and Ancillary Offices Electrical Upgrade
|
€745,268.67
|
|
2025
|
DFTC, ARW Training Centre Roofing (Old Cinema)
|
€440,214.29
|
|
2025
|
DFTC, New CIS Workshop Facility
|
€8,783,510.76
|
|
2024
|
DFTC Garaging X 2
|
€4,133,275.32
|
|
2023
|
DFTC Cadet School Headquarters
|
€4,741,282.89
|
|
2023
|
DFTC Engineers Logistics Office
|
€583,436.69
|
|
2022
|
DFTC, Engineer Storage Facility
|
€791,222.30
|
|
2021
|
DFTC, Provision of a new Electric Target Range
|
€1,218,556.90
|
In addition, my Department also allocates funding each year to the Defence Forces for the maintenance, repair and upkeep of its building stock. This year a devolved budget of €13.5 million was assigned by my Department to the Defence Forces for these tasks. The individual prioritisation of specific projects to be carried out is solely a matter for the Defence Forces in keeping with the delegated nature of this budget.