127. Deputy Aidan Farrelly asked the Minister for Culture, Communications and Sport to provide the total number of successful applicants to the Large Scale Sport Infrastructure Fund; the applicant name; project details; status of the project; and the spend to date on each project from the 2024 fund, in tabular form. [40769/26]

Amharc ar fhreagra

Freagraí scríofa

The Large-Scale Sport Infrastructure Fund (LSSIF) was established to provide Exchequer support for larger sports facility projects, typically those requiring investments greater than the maximum available under the Community Sport Facilities Fund.

Details of grants awarded under the LSSIF are available on the Department's website at www.gov.ie/en/service/6f3f3-large-scale-sport-infrastructure-fund-lssif-2024/#lssif-allocations.

In 2024, the second round of LSSIF received an unprecedented demand for funding. Grants totalling €173 million were awarded to 35 projects. Details of the projects and their current status are detailed in the table below.

Project Title

County

Updated Project Description

Status

Water Activity Centre (Carlow)

Carlow

To develop a water hub activity centre which contains boat storage & amenities for rowing, dragon boat & youth service as well as changing facilities, training & fitness room, parking, public seating/terrace, pedestrian boardwalk linking to the town park

Tender Stage

Cavan Regional Sports Campus

Cavan

To development of Phase 1 of the Cavan Regional Sports Campus – Progress. Phase 1 includes a covered sports arena with playing pitch, spectator seating, and other ancillary accommodations. It includes a leisure sports centre building, which includes changing facilities, multi-purpose rooms, reception and ancillary accommodation. It includes 4 sand-carpet GAA pitches with perimeter fencing & lighting, 1 synthetic hockey/multi-sport pitch with perimeter fencing & lighting, a cricket practice area and catch-nets.

At Approval Gate 1

Clare GAA, Centre of Excellence (Caherlohan)

Clare

To complete the development at Caherlohan by developing two new playing pitches, adding floodlights at two existing pitches, constructing an equipment store, improve site access and car parking, install a covered stand at one pitch and develop a new wall ball facility suitable for multi sports as well as a sensory garden and public allotment area.

At Approval Gate 1

Athletics Track - Mallow Carhookeal

Cork

To develop an athletic running track to IAAF standards to include a car park, floodlighting, and street lightning.

Preparing documentation for Approval Gate 1

Cork NW Sports Hub (Castleview AFC)

Cork

To develop an all-weather facility.

Tender Stage

ATU Letterkenny Regional Sports Activity Hub (Phase 2)

Donegal

To develop Phase 2, which includes a full-size GAA (multi-sport) pitch with perimeter fencing and floodlighting, four synthetic 5 a side pitches with floodlighting, an entrance road, car park as well as a pavilion building, which includes a spectator stand, changing rooms, studios, meeting and multipurpose spaces, and ancillary areas. Phase 2 also includes a site compound building including substation, a switch room, oil tank and generator, a sprint track, landscaping , retaining walls, ramps and external stairs and a bicycle shelter

Tender Stage

Morton Stadium

Dublin

To develop Phase 1, which includes the demolition of the east stand and the construction of a new single-storey indoor athletes training facility. The new training facility will incorporate a full indoor 8 lane 100-metre track, high jump area, high-performance gymnasium, reception, medical and physiotherapy treatment spaces, changing village, public toilets, and storage.

Rescoping

Tallaght Stadium

Dublin

To upgrade to LED floodlighting.

Tender Stage

Hyde Park, Dalkey

Dublin

To develop an indoor sports hall, wall ball, gym, fitness studio, video analysis room, training room, changing rooms, an office, physio room, storage space, lobby, toilets, services.

At Approval Gate 1

Spawell Cluster Facility

Dublin

To develop Phase 1, which will deliver two full pitches and a temporary dressing-room area for community use as well as floodlighting and site works.

At Approval Gate 1

Marlay Sports Hub

Dublin

The proposed development of a Sports Hub in the park to cluster the different sports facilities together.

Rescoping

Dalymount Park Redevelopment

Dublin

To redevelop Dalymount Park

At Approval Gate 1

Kinvara Hockey Club

Galway

To develop Phase 1, which includes a full-size FIH-certified 2G sand-dressed hockey pitch with an engineered base and full drainage, competition-standard floodlighting, perimeter fencing and ball-stop netting, boundary treatments with water and roadway access, bus and car parking, along with goals, dugouts, pitch-equipment storage and bleachers.

At Approval Gate 1

St Jarlath’s, Tuam

Galway

To develop a full-size 4G floodlit all-weather synthetic pitch and to redevelop the existing grass training pitches into a full-size grass playing pitch and a sports pavilion.

At Approval Gate 1

Killarney RFC

Kerry

To a clubhouse, which includes changing rooms, 25 individual shower units, referees changing room/Shower Unit, accessible toilet with room for shower a multipurpose meeting room, first aid room, gym and equipment room.

Tender Stage

Derreen Community Complex, Killarney

Kerry

In phase 3 and 4 of a new development on a brown field site. Proposed multi-sports facility – Indoor Sports Hall, Sprung Floor Dojo/Studio, Gym, Social Hub and Café, Multipurpose Meeting room.

Awaiting direction from Grantee

Fitzgerald Stadium, Killarney

Kerry

To construct a new West Terrace and improve the Northern Terrace, Eastern Terrace and the O'Sullivan stand along with ancillary works.

At Approval Gate 1

Sallins Park Community Sports Centre ( Kildare co co )

Kildare

To develop Phase 1, which includes 1 synthetic pitch, 2 sand pitches, 2 grass training pitches, access road and paths a car park and the installation of services.

At Approval Gate 1

Golf Ireland HP Centre

Kildare

The proposed development of high-performance centre for national squads.

Tender Stage

Naas Cross-Community Development Project (Naas GAA)

Kildare

To develop an all-weather pitch, a sand-based pitch and a gym.

At Approval Gate 1

Shannonside Regional Recreation Centre

Leitrim

To develop a 4G pitch with floodlights,

8-lane athletics running track, an athletics track spectator terrace including storage, an upper pitch terrace including storage and toilet block and site works and landscaping

At Approval Gate 1

Patrickswell GAA

Limerick

To develop a natural turf full-sized playing pitch, a natural turf training area, a new walkway/running track around the perimeter of the main pitch, and a training area, 8 floodlighting columns to the main pitch, ball stop nets to northern and southern goal ends of the main pitch, biodiversity planting around the walkway/running track.

Construction Phase

City North Arena

Limerick

To develop an indoor arena

Awaiting direction from Grantee

St. Oliver’s ETB

Louth

To develop a combination of single-story and two-story structure with a general-purpose sports hall central to the development, which will be equipped to host various sporting events and activities

At Approval Gate 1

Mayo Sports Campus

Mayo

To develop of a state-of-art Community Sports Campus

At Approval Gate 1

Seafield Community Facility

Meath

To develop a vibrant, multi-functional space catering to the needs of existing clubs and future users

Awaiting direction from Grantee

Trim Arena

Meath

To develop a single and two storey indoor athletics training building, supported by ancillary outdoor facilities. The indoor building includes a 60m indoor sprint track, long jump and high jump areas, strength & conditioning and technical training space, storage, meeting room, toilets, and supporting amenities

Preparing documentation for Approval Gate 1

St. Colmcille’s

Meath

To develop 2 full-size grass pitches

groundworks, fencing, netting.

Tender Stage

Killeevan Sarsfields

Monaghan

To develop a new playing field, access road, car park and civil works.

At Approval Gate 1

Edenderry Pool

Offaly

To develop a new competition standard swimming pool facility and fitness centre. It will feature a FINA Standard 6-lane, 25m short

course swimming pool complete with approved diving blocks, a viewing area, a children's pool, and a hydrotherapy recovery area with hot and cold baths. Additionally, there will be a relaxation zone equipped with a sauna and steam room, as well as an ultra-modern strength & conditioning gym.

At Approval Gate 1 for Design

Roscommon GAA - Dermot Earley Centre of Excellence

Roscommon

To develop a Centre of Excellence on a green field site of 23.3 acres. .

Waiting on decision in relation to IIP Funding

Sligo Rovers FC Showgrounds

Sligo

To redevelop Sligo Rovers Stadium.

Waiting on decision in relation to IIP Funding

East Coast Hub, Gorey

Wexford

To develop a national-standard astro-turf hockey pitch, a full 400m tartan running track, a full-sized cricket pitch, temporary changing facilities, new site access, and all associated ancillary and enabling works.

At Approval Gate 1

Wexford GAA, Centre of Excellence (Ferns)

Wexford

To develop Phase 3 which consists of a new building incorporating six additional dressing rooms, meeting rooms, a gym, performance analysis room, medical/physio room, office space, a spectator viewing area for the main pitch, and the development of a new 4G pitch.

At Approval Gate 1

Wexford FC

Wexford

To develop Phase 1, which will deliver a 1,500-seater stand integrated with a 10,000 sq. ft pavilion, along with a natural grass pitch and LED floodlighting.

At Approval Gate 1

Roinn