Schools Building Projects

Dáil Éireann Debate, Tuesday - 23 June 2026

Tuesday, 23 June 2026

Ceisteanna (316)

John Connolly

Ceist:

316. Deputy John Connolly asked the Minister for Education and Youth for an update on any planned enhancement and/or development works at a school (details supplied); and if she will make a statement on the matter. [47054/26]

Amharc ar fhreagra

Freagraí scríofa

The project at Coláiste Croí Mhuire has been devolved to the Board of Management for delivery. The approved brief provides for an extension to accommodate 200 pupils and two Special Education Needs (SEN) classrooms.

The project is currently at Stage 2a, which is the stage the design is fully developed and cost-planned in preparation for seeking statutory approvals. A Stage 2a Addendum was received by the Department in late March 2026 and is presently under review by the Department’s Professional and Technical Team.

Progression to Stage 2b can only be authorised once this review is complete and all technical, planning, and cost considerations have been satisfactorily addressed. Until this process concludes, it is not possible to provide a definitive timeline for approval to proceed to Stage 2b or for the overall project completion.

Since 2020, my department has invested over €6.9 billion in our schools throughout the country under the National Development Plan, involving the completion of over 1,400 school building projects along with over 4,000 small-scale improvement works to meet priority maintenance needs and advance energy efficiency and climate goal. In addition, repurposing and optimisation of existing accommodation capacity across the school estate has been a key enabler of timely, local provision of special class capacity in a way that supports best practice in inclusion and integration. Circa 80% of new special classes in 2025/26 are being facilitated in repurposed classroom accommodation. This investment has delivered real benefits for school communities.

A total capital allocation of €7.55 billion for the Department of Education and Youth has been confirmed for the period 2026-2030 under the National Development Plan. As part of this NDP allocation my department will place a strong emphasis on provision for children with special educational needs, with a particular focus on meeting annual school place needs. In relation to project rollout for Large-Scale projects and Additional School Accommodation scheme projects, the approach will be to continue to maximise the capacity of the existing school estate as much as possible in the first instance and provide necessary additional capacity through targeted and prioritised project rollout over the course of 2026 to 2030 period to meet the most urgent and prioritised needs.

As part of the NDP Implementation Plan for the education and youth sector, a first tranche of projects to progress to tender and/or construction during 2026 and 2027 was published in January 2026. Prioritisation will continue to identify further tranches of projects to proceed to tender and construction over the NDP period, with stakeholder consultation to commence in June 2026.

Our NDP Implementation Plan will optimise outputs from the NDP allocations, with a strong focus on maximising existing school capacity, progressing priority projects where local capacity across schools in the area is insufficient, and ensuring delivery that is affordable, offers value for money, and meets functional needs.