207. Deputy Aidan Farrelly asked the Minister for Transport if he will provide an update in respect of IT projects (details supplied) to include delivering and or development third party; the amount expended to date in respect of consultancy and project management fees; if he will indicate the timeline to rollout of each project; if he will clarify whether each project is currently within budget and if not the amount in excess of budget the project has slipped. [51230/26]

Amharc ar fhreagra

Freagraí scríofa

The table below sets out the details requested by the Deputy in respect of projects managed directly by my Department.

Project

Development Third Party

Description

Amount Expended to Date

Project Rollout

Within Budget

Amount in Excess

Comment

Road Transport Operator Licensing

The contract was originally awarded to Fujitsu Ireland. Following Fujitsu Ireland’s withdrawal from the Irish market, Fujitsu Portugal assumed responsibility as the primary contractor for the project.

Development of the new Road Transport Operator Licensing (RTOL) system to meet current and future requirements.

€3,792,893.69, of which €576,861.14 is attributable to project management services.

The project commenced in 2022 and went live on 8 November 2025, followed by a hypercare support period which concluded on 12 January 2026.

Yes, the project is currently operating within its approved budget and is expected to remain within budget following completion of the final milestone payment.

N/a

The final project milestone payment has not yet been made, as the required technical documentation remains outstanding.

European maritime single window

Completed procurement documents shortly will be published to the market.

FinOG is Ireland’s implementation of the European Maritime Single Window Environment (EMSWe), being delivered in accordance with EU legislation.

€292,778

(Project Management services are provided by Department PMO to date – no fulltime PM appointed)

The planned project completion date is Q4 2029.

N/a

N/a

Following the analysis and factoring in the extension of the support contract to a 10-year term, the total estimated contract value is €10,180,725

I have referred the Deputy’s question to the agencies under the remit of my Department for direct response in relation to the following projects:

• NTA – NGAVL Implementation

• RSA – P102 CoVIS Transformation

• RSA – Transformation Programme

• TII – One MIS