305. Deputy Mark Wall asked the Minister for Housing, Local Government and Heritage the up-to-date position with a social housing project in County Kildare (details supplied); the number and type of houses to be constructed; and if he will make a statement on the matter. [52578/26]

Amharc ar fhreagra

Freagraí scríofa

The subject site is part of a multi-site programme of four social housing developments currently being tendered by the local authority. Funding for this project has been approved through the Social Housing Investment Programme (SHIP).

Based on the current programme it is expected that construction contract will be awarded in Q4 2026.

Breakdown of units for the subject site is as follows:

Apartment Unit Mix Number of Apartments

1 bed unit (2P) 18

2 bed unit (4P) 1

Total 19 apartments

1 bed house (Bungalow) (2p) 4

2 bed house (4p) 24

3 bed house (5p) 20

4 bed house (7p) 6

Total 54 houses