Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Regeneration Projects

Dáil Éireann Debate, Thursday - 16 July 2026

Thursday, 16 July 2026

Ceisteanna (362)

Thomas Gould

Ceist:

362. Deputy Thomas Gould asked the Minister for Housing, Local Government and Heritage the timeline for the full completion of the Cork City Northwest Quarter Regeneration Plan. [54358/26]

Amharc ar fhreagra

Freagraí scríofa

Based on information provided to my Department by Cork City Council I can advise of the timeline below for delivery of the Cork North West Quarter Regeneration (CNWQR) Social Housing projects, by phase. Please note that Table 1 below includes social housing projects that are fully approved; Table 2 includes social housing projects that are going through the approval process.

Responsibility for the progression of individual projects and the associated delivery timelines lie with Cork City Council.

Table 1.

Project Name

No of Units

Project Status

Construction Status

Projected Delivery Date/Completion Date

CNWQR Croppy Boy Phase 1

24

Contract Awarded

Onsite

Q3 2026

CNWQR Knocknaheeny Phase 1B

29

Complete

Completed

Q3 2017

CNWQR Knocknaheeny Phase 1C

41

Complete

Completed

Q4 2025

CNWQR Knocknaheeny Phase 2A

47

Complete

Completed

Q4 2019

CNWQR Knocknaheeny Phase 2B

38

Contract awarded

Onsite

Q4 2026

Regen CNWQR Knocknaheeny Phase 3B

62

Contract Awarded

Onsite

Q2 2027

Table 2.

Project Name

No of Units

Project Status

Construction Status

Projected Delivery Date/Completion Date

CNWQR Phase 4C West

20

Pre Planning

Not Started

Q2 2028

CNWQR Knocknaheeny Phase 4 F

23

Pre Planning

Not Started

Q4 2028

CNWQR Knocknaheeny Phase 3C

24

Pre Planning

Not Started

Q4 2028

CNWQR Knocknaheeny Phase 3A

15

Pre Planning

Not Started

Q4 2028

CNWQR Knocknaheeny Phase 1D East

14

Pre Tender

Not Started

Q4 2028

Regen CNWQR Knocknaheeny Phase 4A

43

Pre Tender

Not Started

Q4 2028

Roinn