Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

School Accommodation

Dáil Éireann Debate, Thursday - 16 July 2026

Thursday, 16 July 2026

Ceisteanna (65)

Colm Burke

Ceist:

65. Deputy Colm Burke asked the Minister for Education and Youth the current status the application by a school (details supplied) under the additional accommodation scheme; the stage the project is currently at; when permission will be given to move to the next stage; and if she will make a statement on the matter. [54073/26]

Amharc ar fhreagra

Freagraí scríofa

Phase 1 of the reconfiguration works St Patrick’s College Gardiner’s Hill was completed in May 2025 and this resulted in new accommodation for the school including a new Technology/Graphics room, modern toilet block, disabled access toilet, a deputy principal's office and improved access to the permanent building of the school. 

My department has had a number of discussions previously with the school authorities in relation to the proposed phase 2 element of the project and is currently exploring a number of options. This review is ongoing and the department has clarified this to the school recently. The department will be in further contact with the school authorities/patron directly on this matter when this review is completed. 

Since 2020, my department has invested over €7 billion in our schools throughout the country under the National Development Plan, involving the completion of over 1,500 school building projects along with circa 4,300 small-scale improvement works to meet priority maintenance needs and advance energy efficiency and climate goal.   In addition, repurposing and optimisation of existing accommodation capacity across the school estate has been a key enabler of timely, local provision of special class capacity in a way that supports best practice in inclusion and integration. Circa 80% of new special classes in 2025/26 are being facilitated in repurposed classroom accommodation. This investment has delivered real benefits for school communities.   

A total capital allocation of €7.55 billion for the Department of Education and Youth has been confirmed for the period 2026-2030 under the National Development Plan.   As part of this NDP allocation my department will place a strong emphasis on provision for children with special educational needs, with a particular focus on meeting annual school place needs.  In relation to project rollout for Large-Scale projects and Additional School Accommodation scheme projects, the approach will be to continue to maximise the capacity of the existing school estate as much as possible in the first instance and provide necessary additional capacity through targeted and prioritised project rollout over the course of 2026 to 2030 period to meet the most urgent and prioritised needs.   

As part of the NDP Implementation Plan for the education and youth sector, a first tranche of projects to progress to tender and/or construction during 2026 and 2027 was published in January 2026.  Prioritisation will continue to identify further tranches of projects to proceed to tender and construction over the NDP period, with stakeholder consultation to commence in June 2026.   

Our NDP Implementation Plan will optimise outputs from the NDP allocations, with a strong focus on maximising existing school capacity, progressing priority projects where local capacity across schools in the area is insufficient, and ensuring delivery that is affordable, offers value for money, and meets functional needs.

Roinn