Schools Building Projects

Dáil Éireann Debate, Tuesday - 29 September 2026

Tuesday, 29 September 2026

Ceisteanna (402)

James O'Connor

Ceist:

402. Deputy James O'Connor asked the Minister for Education and Youth if she will provide an update to this Deputy in relation to application for an extension for a school building in County Cork (details supplied); whether her Department are using documents from a submission in April 2026 or otherwise; if she will provide a timeline on when the school management can expect a completion of the latest stage; and if she will make a statement on the matter. [68558/26]

Amharc ar fhreagra

Freagraí scríofa

The school to which the Deputy refers was approved under the Additional School Accommodation (ASA) Scheme for the provision of one Mainstream Classroom, one Special Education Teaching (SET) room and one Special Educational Needs (SEN) room.  The project has been devolved to the school authority for delivery.

The school initially submitted a Stage 1/2a Report that extended beyond the scope of works approved by the Department. As a result, the school was requested to submit a revised report aligned with the approved project scope.

The revised Stage 1/2a Report has since been received and reviewed in accordance with the Department's Infrastructure Guidelines, taking into account the priorities and funding framework set out under the National Development Plan. Following this review, a further request for information and clarification issued to the school.

The school has responded to this request and the matters raised are currently being considered by the Department as part of the ongoing review process.

Progression of the project to the next stage will be considered as part of the Department's ongoing review and prioritisation of projects under the National Development Plan.

Question No. 403 answered with Question No. 364.