The National Broadband Plan (NBP) is being delivered through investment by commercial enterprises coupled with intervention by the State in those parts of the country where private companies have communicated, they have no plans to invest.
The State-led intervention was approved by the European Commission through its formal State aid decision in November 2019.
The Intervention Area (IA) identified as the Amber area on the Department’s NBP Map was identified by two mechanisms.
Firstly, the scope of the Intervention Area was identified through an extensive mapping exercise conducted by the Department since 2013 to identify areas where market failure for broadband exists.
Secondly, the scope of the IA, premises and area, was finalised following the 2019 Mapping Consultation which sought plans from commercial operators over the 7-year period of the planned State-led deployment.
The output of the 2019 Mapping Consultation - following the submissions from commercial operators - identified locations i.e. the IA, where these operators did not have existing or planned high speed broadband availability.
All premises within the Intervention Area are justified, however the IA is dynamic and continues to grow through updates made to GeoDirectory and updated on the NBP Map each quarter.
The State Intervention Area includes:
• 564,000 premises
• 1.1 million people
• Over 65,000 farms
• 44,000 non-farm businesses
• 679 schools
There is a contractual requirement under the Project Agreement, for all premises that are located within the IA, to be delivered by NBI.
There are however steps taken within the process of updates made to the IA to ensure high density populations, for example new estates planned and built adjoining to the IA, that are covered or likely to be covered by commercial operators, are removed from scope.
A robust governance structure has been established within the Department to monitor contract compliance across technical, governance, compliance, financial, commercial, and project implementation work streams and includes a NBP Senior Management Team.
To protect the State investment and ensure that the NBP milestones and deliverables are met, the contract has been designed to include extensive protections, quality checks and reporting and monitoring obligations.