634. Deputy Peadar Tóibín asked the Minister for Housing, Local Government and Heritage the average construction costs incurred by local authorities, per house, in the construction of social houses. [55234/25]

Amharc ar fhreagra

Freagraí scríofa

My Department assesses, approves and records local authority social housing delivery on a project basis, rather than on the basis of individual unit types.

As Social Housing Investment Programme funded construction projects by local authorities must, like all publicly-funded construction programmes, comply with the Infrastructure Guidelines (Public Spending Code) and Capital Works Management Framework, my Department periodically issues Basic Unit Costs (BUCs) for each local authority area, for use as a key benchmark for the development and costing of scheme designs at capital appraisal stage. While not a record of actual delivery costs, BUCs are based on an analysis of returned data from tendered social housing schemes over an extended period and updated based on published tender index information as required.

To monitor tender cost trends and to inform BUC levels, my Department analyses the tender data for the construction cost element of new build schemes approved under the SHIP & CAS four stage approval processes for each unit type, where sufficient information is available to allow such costs to be extrapolated and where the information available is appropriate for comparison purposes.

Outlined in the table below are average construction costs per unit (incl. VAT), for each Local Authority, recorded as part of the aforementioned analysis for projects tendered in the years 2023, 2024 & 2025 (to July).

The table also sets out the range of average unit costs (across different projects) for each local authority. The range of costs recorded vary, depending on design, mix of unit types (e.g. bedroom numbers, apartment/house); and on the level of abnormal requirements for each scheme, for instance existing site conditions, demolitions, service diversions, site access requirements. Average abnormal costs are also separately identified in the below tables.

2023 – July 2025

Construction Costs (incl. abnormals)

Abnormal Costs

Local Authority

Average Cost Per Unit €

Range of Costs Per Unit €

Average Cost Per Unit €

Carlow

215,423

215k - 215k

10,289

Cavan

253,368

192k - 294k

31,728

Clare

275,980

257k - 306k

36,332

Cork City

381,400

240k - 420k

29,488

Cork County

280,978

165k - 372k

31,544

Donegal

268,900

236k - 329k

35,058

Dublin City

448,900

449k - 449k

31,025

Fingal

312,632

271k - 324k

32,599

South Dublin

385,666

350k - 437k

22,609

DLR

351,136

252k - 376k

29,569

Galway City

341,589

226k - 355k

26,822

Galway County

259,328

232k - 272k

32,527

Kerry

345,203

231k - 368k

52,672

Kildare

371,346

371k - 371k

62,131

Kilkenny

269,848

260k - 293k

35,815

Laois

290,221

228k - 344k

32,632

Leitrim

182,663

183k - 183k

2,614

Limerick

302,932

196k - 361k

48,445

Longford

275,711

246k - 285k

28,849

Louth

329,426

303k - 368k

58,079

Mayo

317,117

262k - 414k

57,051

Meath

303,255

222k - 374k

40,589

Monaghan

307,044

291k - 342k

21,515

Offaly

283,215

283k - 283k

45,664

Roscommon

237,273

211k - 277k

10,970

Sligo

291,804

256k - 332k

33,087

Tipperary

275,893

219k - 287k

42,960

Waterford

276,252

221k - 298k

53,735

Westmeath

269,855

250k - 460k

29,576

Wexford

322,640

262k - 359k

43,407

Wicklow

328,923

170k - 387k

44,152

The costs in the above table relate to the construction element only of the all-in delivery cost. Other items that make up the all-in total include:

• Design/technical fees: Design fees vary from project to project, depending on the location, size and complexity of a scheme (and depending on whether design services are provided by a local authority in-house or via external appointment). As a guideline/indicator, design fees are generally expected to range between 7.5% to 12.5% of construction costs.

• Land cost: Land costs will vary significantly from project to project, depending on location and ownership status (i.e. land costs could vary from existing local authority land at no cost to land purchased at market value).

• Utilities: Connection fees for Irish Water, ESB, gas, etc. As a guideline/indicator, utility connection costs are generally in the order of €7k per unit.

• Other Costs: Other items that make up the all-in delivery cost can include site investigations/surveys, archaeological requirements, Percent for Art contributions - and will vary from scheme to scheme.